Multiplex Vancouver: 625 Permits, Now Double New Houses, and Slower to Approve (October 2026)

The City of Vancouver has issued 625 building permits for multiplexes since the first one in 2024, and this year they outnumber permits for new single-family houses two to one: 237 to 119, from January 1 to October 28.

That's the clearest sign yet that the R1-1 zoning Council adopted in September 2023 changed what gets built on a Vancouver lot. But the same permit data shows two things the headlines don't. Multiplex permits are down 9% on the same stretch of 2025, and the median multiplex building permit issued this year took 192 days from the permit number being created to issue, longer than a house (142) and longer than multiplexes took a year ago (168.5).

Below: what the City's permit records say, where multiplexes are going, how long they take, and what detached and townhouse prices mean for anyone thinking of building one or buying a unit in one. The permit numbers come straight from the City's open data, and I've explained exactly how I counted.

Multiplex permits issued, 2024 to Oct 28, 2026625first issued 2024/06
Multiplex vs house permits, Jan 1–Oct 28, 2026237 vs 119multiplexes −9% vs same period 2025
Median days to permit, multiplex, 2026192168.5 in 2025; 142 for a house
Vancouver East detached benchmark, Sept$1.63M−13.9% in 3 years

Sources: City of Vancouver Open Data, Issued building permits (new-building permits issued to October 28, 2026; EstateBlock analysis); Greater Vancouver REALTORS®, September 2026 stats package.

Multiplexes vs houses, by the permit count

New low-density building permits, January 1 to October 28 City of Vancouver new-building permits issued, same window each year
  • Houses
  • Duplexes
  • Multiplexes

Source: City of Vancouver Open Data, Issued building permits (new-building permits issued to October 28, 2026; EstateBlock analysis)

Show the numbers
HousesDuplexesMultiplexes
2019427910
20202931150
20212081590
20223952890
20232561920
202418915523
2025142155261
2026119135237

Between 2019 and 2023, the same January-to-late-October window brought 208 to 427 new-house permits a year. In 2026 there have been 119. Multiplexes went from 23 in that window of 2024 to 261 in 2025 and 237 this year. Duplexes have slipped to 135, from 289 in 2022.

Put another way: of the 689 new low-density building permits this year (houses, duplexes, laneways and multiplexes together), 34% were for multiplexes. In 2023, before the first multiplex permit, the same four categories totalled 716.

City of Vancouver new-building permits issued by type, full years
YearHousesDuplexesLaneway housesMultiplexes
20194791124720
20203381423820
20212662122970
20224433364390
20232832202960
202421520139960
2025167196365328
2026 (to Oct 28)119135198237

Source: City of Vancouver Open Data, Issued building permits (new-building permits issued to October 28, 2026; EstateBlock analysis). Multiplex = project description contains "multiplex"; one project can have more than one permit.

Laneway houses are the other number to watch. They're down from 321 to 198 in the same window, a 38% drop. A laneway was the add-a-unit option for an owner keeping the main house; a multiplex is usually a full rebuild. The permit mix suggests the lots that do get redeveloped are going to the bigger option.

Is the multiplex boom slowing?

Multiplex building permits issued, by quarter City of Vancouver new-building permits with “multiplex” in the description. *Q4 2026 = October 1 to 28

Source: City of Vancouver Open Data, Issued building permits (new-building permits issued to October 28, 2026; EstateBlock analysis)

Show the numbers
Multiplex permits
Q2 '242
Q317
Q441
Q1 '2553
Q278
Q397
Q4100
Q1 '2666
Q248
Q393
Q4*30

Permits climbed every quarter through 2025 and peaked at 100 in the last quarter of the year. Then they fell to 66 and 48 before bouncing back to 93 in the third quarter. October alone has 30.

So it's a slowdown, not a stall. With a median of about six months from permit number to issue, permits issued today reflect decisions made many months earlier. The City's own City of Vancouver memo to Mayor and Council on the R1-1 zone, May 29, 2025 counted about 370 multiplex applications accepted from November 2023 to March 31, 2025, covering about 1,500 homes. It hasn't published an updated count that I can find.

That memo is also the best guide to what's in the pipeline. Of those applications, 45% were for four units, 29% for three, 18% for six and 9% for five. 70% used a courtyard layout (separate front and rear buildings), which is why one project often shows up as two permits. Parking averaged 0.83 spaces per unit.

Multiplex applications by number of units Share of about 370 applications accepted, November 2023 to March 31, 2025
3 units28.6%4 units44.6%5 units8.9%6 units17.8%

Source: City of Vancouver memo to Mayor and Council on the R1-1 zone, May 29, 2025

Show the numbers
UnitsShare of applications
3 units28.6%
4 units44.6%
5 units8.9%
6 units17.8%

How long a permit takes

The City's data records the number of days between a permit number being created and the permit being issued. It's the closest public measure of approval time, though the clock can include time the applicant spends revising drawings.

Median days from permit number created to permit issued New-building permits issued in each year (2026 = to Oct 28). Multiplex permits start in 2024
  • Houses
  • Duplexes
  • Multiplexes

Source: City of Vancouver Open Data, Issued building permits (new-building permits issued to October 28, 2026; EstateBlock analysis)

Show the numbers
HousesDuplexesMultiplexes
2022250243—
2023274331—
2024233161108
2025177142168
2026142115192

The trend runs in opposite directions. Median processing time for a new house fell from 274 days in 2023 to 142 this year, and duplexes from 331 to 115. Multiplexes went the other way: 108.5 days for the first 60 permits in 2024, 168.5 in 2025 and 192 so far in 2026.

Some of that is the mix. The first permits out the door in 2024 may have been the simplest projects. Some of it may be volume: at the late-2025 peak the City was issuing about 33 multiplex permits a month. Either way, if you're planning one, budget at least six months for the building permit alone, and I'd assume longer.

The declared construction value on a multiplex permit has a median of $836K this year, up from $779K in 2024. That figure is per permit, so a two-building project carries two of them, and it's the value the applicant declares, not a final build cost.

Where multiplexes are being built

Multiplex building permits by neighbourhood, 2024 to Oct 28, 2026 City of Vancouver local areas (the City's 22 planning areas, not MLS® sub-areas). 6 permits have no local area and aren't shown
Hastings-Sunrise101Kensington-Cedar Cottage62Kerrisdale54Dunbar-Southlands49Arbutus Ridge43Renfrew-Collingwood42Victoria-Fraserview39Shaughnessy39Sunset37Riley Park32West Point Grey30Killarney29Kitsilano24Marpole23Oakridge9South Cambie3Mount Pleasant3

Source: City of Vancouver Open Data, Issued building permits (new-building permits issued to October 28, 2026; EstateBlock analysis)

Show the numbers
Local areaMultiplex permits
Hastings-Sunrise101
Kensington-Cedar Cottage62
Kerrisdale54
Dunbar-Southlands49
Arbutus Ridge43
Renfrew-Collingwood42
Victoria-Fraserview39
Shaughnessy39
Sunset37
Riley Park32
West Point Grey30
Killarney29
Kitsilano24
Marpole23
Oakridge9
South Cambie3
Mount Pleasant3

Hastings-Sunrise leads by a wide margin with 101 permits, followed by Kensington-Cedar Cottage (62) and Kerrisdale (54). The list splits roughly between the east side's big blocks of older houses (Hastings-Sunrise, Kensington-Cedar Cottage, Renfrew-Collingwood, Victoria-Fraserview, Sunset) and the west side's large lots (Kerrisdale, Dunbar-Southlands, Arbutus Ridge, Shaughnessy, West Point Grey).

The City's memo saw the same split in applications: 52% on east-side sites, 38% west and 10% central, with six-unit projects mostly on the west side's 50-foot-plus lots. Some local areas barely appear: Mount Pleasant and South Cambie have 3 each, and Grandview-Woodland has 0.

The land math: detached prices and townhouse prices

A multiplex starts with buying a detached house, so detached prices set the floor. They've fallen. GVR's benchmark detached price in Vancouver East was $1.63M in September, −7.7% in a year and −13.9% over three years. Vancouver West was $2.92M, −8.7% in a year and −16.4% over three. Three years ago is almost exactly when R1-1 was adopted. My read: whatever the new zoning did for development lots, it hasn't been enough to hold up the price of a typical detached house.

MLS® Home Price Index benchmarks, Vancouver East and West
Area and typeBenchmark, Sept 20261 year3 years5 years
Vancouver East: Detached$1,630,500−7.7%−13.9%−3.6%
Vancouver East: Townhouse$980,400−7.9%−13.1%−4.1%
Vancouver East: Apartment$634,800−5.2%−11.1%−1.3%
Vancouver West: Detached$2,916,100−8.7%−16.4%−12.0%
Vancouver West: Townhouse$1,298,500−5.5%−8.4%−2.4%
Vancouver West: Apartment$761,800−5.2%−9.8%−3.6%

Source: Greater Vancouver REALTORS®, September 2026 stats package (MLS® HPI benchmark prices, sales-based).

Benchmark detached price divided by the number of units (land only, before construction, fees and financing)
Units on the lotVancouver East: land per unitVancouver West: land per unit
3 units$544K$972K
4 units$408K$729K
6 units$272K$486K

Source: EstateBlock calculation from Greater Vancouver REALTORS®, September 2026 stats package. The benchmark is a typical house, not a typical development lot; actual lot prices vary widely by size and location.

This is rough, deliberately. A four-unit project on a benchmark-priced East Van house carries about $408K of land per unit before a single stud goes up. The benchmark townhouse in Vancouver East is $980K, down 7.9% in a year. Construction, City charges and financing all have to fit between those two numbers. My read: that's why falling townhouse prices hurt a multiplex project more than cheaper houses help it.

The asking side tells a similar story. On EstateBlock today, Vancouver has 1,326 houses for sale at a median asking price of $2.77M and 76 median days on market, and 509 townhouses at a median $1.40M and 49 days. Townhouses are asking more per square foot than houses, $1,035 vs $982. I'd watch that gap: it's the premium new multi-unit space needs for a multiplex to make sense. These are asking prices of active listings, not sales.

Vancouver houses for sale, median asking$2.77M1,326 listings; $982/sq ft
Vancouver townhouses for sale, median asking$1.40M509 listings; $1,035/sq ft
Median days on market: houses vs townhouses76 vs 49active listings

Source: EstateBlock.com Vancouver listings, snapshot taken October 29, 2026 (active listings, asking prices).

If you're shopping for a unit in a multiplex, townhouses are the closest comparison: you can browse Vancouver townhouses for sale on EstateBlock. For the townhouse market in more detail, see my Vancouver townhouse prices breakdown.

What's changing next

The rules are under review again. The City's multiplex page on Shape Your City says staff are reviewing and updating policies and regulations related to multiplexes and other low-density housing options, in response to Council motions passed in 2025 and 2026 and the province's small-scale multi-unit housing legislation (Bill 25). Public engagement is expected to begin in fall 2026 and continue into early 2027, and staff expect to report back to Council in early 2027.

Under the current R1-1 rules, per the City's memo, a lot can hold three to six ownership units (strata tenure) or up to eight secured rental units. The zone covers about 65,000 lots, over half the City's land. Minimum parking requirements were removed citywide in June 2024.

I won't guess what the review will change. If you're buying a lot to build, or selling one to a builder, check the rules in force on the day you apply. For how the province's Bill 44 works lot by lot, see my Bill 44 explainer.

What I'd do

For the wider market, see my Greater Vancouver market update, and for how many homes are actually being started across the region, Vancouver housing starts.

FAQ

How many multiplexes have been approved in Vancouver?

The City of Vancouver issued 625 new-building permits with “multiplex” in the project description from 2024 to October 28, 2026: 60 in 2024, 328 in 2025 and 237 in 2026 so far. One project can need more than one permit, so the number of projects is lower. The City's May 2025 memo counted about 370 applications (about 1,500 homes) accepted to March 31, 2025.

How many units can a Vancouver multiplex have?

Under the R1-1 zone adopted in September 2023, a lot can have three to six strata (ownership) units, or up to eight secured rental units. The City is reviewing multiplex rules, with engagement from fall 2026 to early 2027.

How long does a multiplex building permit take in Vancouver?

The median multiplex permit issued in 2026 (to October 28) took 192 days from the permit number being created to issue, up from 168.5 days in 2025. The median for a new single-family house in 2026 was 142 days. Source: City of Vancouver open data.

Which Vancouver neighbourhoods have the most multiplexes?

By building permits issued from 2024 to October 28, 2026: Hastings-Sunrise (101), Kensington-Cedar Cottage (62), Kerrisdale (54), Dunbar-Southlands (49) and Arbutus Ridge (43).

Sources

  1. City of Vancouver Open Data: Issued building permits (dataset)
  2. City of Vancouver Open Data: API export used (new-building permits since 2019)
  3. City of Vancouver: Memo to Mayor and Council, update on the R1-1 Residential Inclusive zone (May 29, 2025)
  4. City of Vancouver, Shape Your City: Multiplex housing or missing middle housing (September 2026 update)
  5. Greater Vancouver REALTORS®: September 2026 stats package
  6. EstateBlock.com: Vancouver houses for sale (snapshot October 29, 2026)
  7. EstateBlock.com: Vancouver townhouses for sale (snapshot October 29, 2026)